An area of 150–300 people takes about 10 working days to plan for, and about a week if everyone answers at once. Interviews do not queue: 30 people at 20 minutes each is 10 hours of work in total, but it can all happen on one day.
| Step | Who | Effort per person | Calendar, if everyone answers at once | Calendar, to plan for |
|---|---|---|---|---|
| Before the start | Sponsor, lead | 1 hour | 1 day | 1 day |
| 1–3. Project, company interview, end-to-end processes | Lead | 1–2 hours | 1 day | 1–2 days |
| 4. Invite the roles | Lead | 30 minutes | Same day | Same day |
| 5a. Inventory interviews | 20–35 people | about 20 minutes | 1–2 days | 3 days |
| 5b. Process interviews, 10–15 maps | Owners, practitioners | 20–40 minutes per interview | 1–2 days, overlapping 5a | up to 5 days, overlapping 5a |
| 6. Review | Reviewer, lead, owners | 1–2 hours per owner | 1 day | 2–3 days |
The parallel part is where the time is won. Inventory and process interviews overlap, and nobody waits for anyone else. What sets the pace is how fast people respond, not how long the interviews take, so the lead's invitation and follow-up matter most.
These are planning estimates, not measured results. Replace them with real figures after the first wave.